Hanon Hall Building

Location

Pécs

Floor area

21.025 m2

Production area size

18.927 m2

Office size

3456 m2

Installed steel structures

70.000 kg

Built-in reinforcing steel

12.300 kg

Green area

5.740 m2

Category

Industrial facilities

In just nine months, Market Építő Zrt. erected the new hall building in Pécs. The building is a warehouse and office building, which can also be used as a manufacturing plant, depending on the requirements. In addition to the main hall building, a gatehouse was constructed, along with a covered communal and hazardous‑waste storage facility, a sprinkler machinery house and tank, a stormwater retention basin, covered bicycle shelters, as well as surrounding paved roadways and car parks.

Construction started with rough land levelling, followed by required subgrade load-bearing capacity using hydraulic binder stabilisation. This was followed by the foundation works and then the installation of precast reinforced concrete elements to serve as the main structural frame of the building. At the same time, work started on the steel structures to provide the rigidity of the building. Once these were in place, the roof was covered with trapezoidal sheets and insulated. The installation of the precast reinforced concrete structural elements was completed with the installation of the plinth elements, followed by the cladding of the building with sandwich panels.

Once the façade cladding was in place, windows and doors were installed, achieving a draft‑ and leak‑free condition. This prepared the site for the most significant phase: preparatory works for the industrial floor installation and specialist trades in the office area. With the bedding layer of the industrial floor completed, electrical, mechanical and dry‑construction works could proceed concurrently. Afterwards, focus shifted to finishing the office area with its specialist trades, and external utilities and road‑building works

Architectural and construction highlights

An industrial floor was installed in the building, 23 cm thick, jointless, steel fibre reinforced, surface hardened and polished to a silky sheen.

During site grading, 42,200 cubic metres of soil was excavated by cutting, followed by back filling with an equal volume of stabilised material

2,100 cubic metres of concrete were used for the precast reinforced concrete structure and 4,380 cubic metres for the industrial floor.

The façade cladding consists of 6,690 square metres of sandwich panels, while a total of 21,025 square metres of material was used for roof insulation and trapezoidal sheeting.

External paved surfaces cover an area of 10,280 square metres.

The building was equipped with 17 sectional and speed gates and 6 hydraulic dock levellers.

Modern IT and mechanical systems support the facility's operational functioning.

The environment has been made greener by planting 40 flowering ash saplings.